Construction Alerts

Overnight Work DPW's contractor has begun overnight electrical work on Castro (Market to 19th Street). We expect the overnight work will continue through next week. The work will be low-impact since the electrical contractor is hand-digging a good portion of the work. He'll use a back-hoe to f...
Overnight Work DPW's contractor has begun overnight electrical work on Castro (Market to 19th Street). We expect the overnight work will continue through next week. The work will be low-impact since the electrical contractor is hand-digging a good portion of the work. He'll use a back-hoe to f...
Project Update The contractor has framed and poured the new curb and gutter on the East side of the 400 block and is scheduled to begin pouring some of the sidewalk next week. We expect the sidewalk pours will begin towards the middle of next week along the East side of the 400 block of Castro. &n...

Posted by on in Construction Alerts
Project Update The contractor has framed and poured the new curb and gutter on the East side of the 400 block. Crews continue the curb & gutter work on the West side of both the 400 and 500 blocks.   Also on the 400 block, crews have begun installing the new irrigation lines on the east ...
    Weekend Work SFWD is expected to continue relocating the water meters. The relocation work is being completed overnight when there is less demand for water service. SFWD will notify you in advance of any interruption. Crews have completed the meter relocation/tie-in work on the ...