Castro Street Improvement Project Update

Posted by on in Construction Alerts
  • Font size: Larger Smaller
  • Hits: 1362
  • Print

Project Update

Construction work continues on the project and next week is going to be busy.

 

On Monday, the contractor is scheduled to begin bus pad demo work on the eastside of Castro in front of Hot Cookie (near Castro Theater) and also in front of the Bank of America (18th Street intersection). The bus pad demo work is scheduled to begin at 7 AM on Monday. Crews will pour the new pads on Wednesday if weather permits.

 

On Tuesday, crews will continue the street base replacement work. The majority of the remaining base work is on the eastside of Castro between 19th and 18th street. Crews are scheduled to pour another 150 cubic yards of concrete on Tuesday.

 

Next week, the contractor is scheduled to begin bulb-out work in front of Harvey's (18th Street intersection) and also Bank of America. Also, tree plantings and irrigation work will continue through the week. 

 

Lastly, SFWD is scheduled to continue tie-in work of the new transmission line on Castro.

 

Thank you for your support of the project.